August18, 2016 (C) Ravinder Singh progressindia2015@gmail.com

BRPL has adopted a new FUNDA to Exploit & Extort Consumers.

1.  They didn’t carryout PRE-MONSOON TRIMMING of Trees pocket money.

2.  There are regular SERVICE LINE Breakdowns mainly affecting a single home but entire area is shut down – over 250 homes – 1000 families for hours.

3.  Even in case Electrical Fire with TOXIC Smoke threatening Consumers – No BRPL Emergency Response Team arrives – No Engineer EVER comes to inspect the site. No Quality of Service-Safety is Observed i.e. Direct Supply to Bus Bar.

4.  Labor cum Contractor arrive at site ‘START NEGOTIATING PRICE’.

5. Priority is Not to Restore Power Supply – BUT EXTORT MAXIMUM Money from affected consumers whose Generators may be Burning Rs.500/- Per Hour of Diesel and Invertors are dead in 1-2 hours.

DELIBRATE NEGLIGENCE & LOOT PROGRAM

Ø    LT Power Lines have SINGLE FEED – At all times when power supply is On I am connected to NATIONAL GRID – but the second LT Circuit Breaker is SWITCHED OFF I AND MY LINE OF HOMES ARE ISOLATED.

Ø    Thus no need to DISCONNECT POWER TO MANY TRANSFORMERS in the area.

Ø    Consumer Service Line faults – it takes two minutes to CUT faulty power cable and restore supply to all but FAULT Line in 10 minutes.

Ø  IT IS POSSIBLE TO RESTORE POWER TO ALL AT Z-22 FAULT BUT FEW DIRECTLY AFFECTED IN 30 MINUTES–THREE PHASE FEXIBLE CABLES CAN BE CONNECTED IN MINUTES.

Ø  But BRPL is planning to First Install A New Pole and Then Fix Power Lines – over Hours & Hour may be 1-2 days.

Z-22 Hauz Khas Tree Fell On LT Line Pole Crash – A Pole Broke into Half

BRPL charge 40,000/- PM as employee cost hire Unskilled & Unqualified, Pole Climbers as Electrical Engineers.

 

There don’t have Electrical Tools Equipment – Ladder arrives in two hours from 1 km.

 

Every time there is a FAULT – some one NEW to the area is ENGAGED.

 

Today a Tree Fell On Power Line in front of Z-22 on road connecting Hauz Khas Market and NIFT.

 

Pole was BROKEN IN HALF and LT power lines Crashed to ground SPARKING and BURNING.

 

Y-Block Power was cut at 7:15 AM – After more than one hour or about 2 hours after the incident – there was No BRPL Emergency Response Team, No Engineer came to the site.

 

LT power lines have Circuit Breakers at Transformers – Switch it off and rest of area except few connections can be Energized in 5 minutes.

 

There was Uphaar Like fire in entire staircase and Lift was filled dense smoke Underground Cable was burning – Police arrived quickly followed by Fire Tender from Safdarjung Airport but there was no BRPL Emergency Response Team.

THEY TAKE MONEY [Private Bribes] FROM CONSUMERS FOR RESTORING FAULTS BUT NEGLECT SERVICE TO 99%. 

 

Ravinder Singh, Inventor & Consultant, INNOVATIVE TECHNOLOGIES AND PROJECTS

Y-77, Hauz Khas, New Delhi-110016, India. Ph; 091- 9871056471, 9718280435, 9650421857

Ravinder Singh* is a WIPO awarded inventor specializing in Power, Transportation,

Smart Cities, Water, Energy Saving, Agriculture, Manufacturing, Technologies and Projects